How long is the shutdown period of the transformer to be retested?

Nov 28, 2021

What tests should be done before the transformer is put into use after being shut down for 1 month or put aside or shut down for more than 6 months?


1. After the transformer is shut down for 1 month, the insulation resistance shall be measured before power transmission is restored, and it can be put into operation only after it is qualified.


2. Before putting into operation, insulation resistance and insulating oil withstand voltage test shall be carried out for transformers that have been put aside or shut down for more than 6 months.


3. The special service life of drainage and irrigation transformers in dry and cold areas can be appropriately extended, but shall not exceed 8 months.


What regulations must be observed for transformer operation and shutdown?


(1) The transformer newly put into operation must undergo 5 impulse tests under rated voltage and 3 times after maintenance.


(2) When the transformer is put into operation, put it into the cooler first. The cooler operates for a period of time (about 15min) and stops after the oil temperature does not rise. When stopping operation, stop the transformer first.


(3) In the neutral point direct grounding system of 110kV and above, when the transformer is put into operation or stopped, the neutral point must be grounded before operation. After the operation, determine whether to disconnect according to the regulations and requirements. The arc suppression coil connected to the neutral point of the transformer shall be pulled out first and then put into operation. Do not connect the neutral points of two transformers to the neutral bus of arc suppression coil at the same time.


(4) In case of power failure, first stop the switch on the load side, and then stop the switch on the power side (from low to high when the multi side power supply is stopped); First pull the transformer side knife switch, and then pull the bus side knife switch. The reverse is true during power operation.


(5) After the standby transformer is put into operation, it shall be determined that the load has been loaded according to the actual position of the equipment and the indication of the electricity meter, so as to cut off the power supply of the operating transformer. Although the transformer on the diagonal and 3 / 2 wiring has been cut off, the heavy gas and differential protection of the transformer will still cause the switch on the closed side to trip. Switch the gas protection to the signal position or withdraw the gas according to the actual situation and site regulations.


(6) Transformers in the station shall not be paralleled for a long time. The low-voltage knife switch can be used to cut off the circulating current at the low-voltage side, and the high-voltage knife switch can be used to cut off the transformer in the no-load station.